What should a Solar PV Supply and Installation Agreement include under Thai law?
The Solar PV Supply and Installation Agreement on this site is an English-language document drafted for use under Thai law. Its 22 clauses cover Definitions and Interpretation; The System and the Works; Site Survey and Roof Structure; Permits, Notifications and Grid Connection; Conditions for Ordering and Installation; Design and Equipment; Installation on Site; and 15 more. The notes below explain Before installation; Payments and receipts; and Stamp duty.
| Clauses in the template | 22 |
|---|---|
| Stamp duty | This Agreement is a hire of work contract. Stamp duty is 1 THB for every 1,000 THB or part of 1,000 THB of the Contract Price. On the price you entered, the duty on the original is the amount the system calculates from the figures entered, and each counterpart carries the amount the system calculates from the figures entered. The Installer pays the duty within 15 days after signing — in money to the Revenue Department if the price is 1,000,000 THB or more, or through the e-Stamp Duty system if the Agreement is signed electronically. |
| Language of the form | English |
| Price of the form on this site | 990 THB |
What the template covers
- Definitions and Interpretation
- The System and the Works
- Site Survey and Roof Structure
- Permits, Notifications and Grid Connection
- Conditions for Ordering and Installation
- Design and Equipment
- Installation on Site
- Completion Date and Delay
- Testing, Commissioning and Acceptance
- Title and Risk
- Price and Payment
- Performance Guarantee
- Warranties and Defects
- Monitoring System, Data and Cybersecurity
- Operation and Maintenance
- Insurance
- Liability
- Termination
- Force Majeure and Change in Law
- Notices
- Governing Law and Disputes
- General
Before installation
- Ask for the civil engineer's signed structural assessment of the roof before any panel is installed (Clause 3.2), and check the engineer's licence on the Council of Engineers website. Keep the assessment with the building documents — the local authority may ask to see it.
- The Customer signs and submits the connection application to the Provincial or Metropolitan Electricity Authority, and any notification to the Energy Regulatory Commission, in the name that appears on the electricity bill (Clause 4.1). Do not let the Installer submit in its own name.
- Do not pay for the main equipment before the roof has been confirmed and the approvals needed before installation have been obtained (Clause 5.1).
- Selling surplus electricity depends on the electricity authority's current programme, its quota and its price. Check the programme terms yourself before relying on export income.
Payments and receipts
- Pay each instalment only against a completed stage (Clause 11.3), and only to the account in Clause 11.4. Confirm any change of bank account by telephone with the person who signed the Agreement.
- For your home, the Installer must give a receipt in Thai each time it receives money (Clause 11.5).
- A Thai company or partnership that pays the Installer withholds 3% of each payment for hire of work and gives a withholding tax certificate. An individual Customer does not withhold.
Stamp duty
- This Agreement is a hire of work contract. Stamp duty is 1 THB for every 1,000 THB or part of 1,000 THB of the Contract Price. On the price you entered, the duty on the original is the amount the system calculates from the figures entered, and each counterpart carries the amount the system calculates from the figures entered. The Installer pays the duty within 15 days after signing — in money to the Revenue Department if the price is 1,000,000 THB or more, or through the e-Stamp Duty system if the Agreement is signed electronically.
Testing and Acceptance
- Attend the commissioning tests if you can, and keep the commissioning report and the performance test data (Clause 9). Using the electricity before Acceptance does not mean you have accepted the System.
- On the day of Acceptance, collect the documents in Clause 9.5, make sure the emergency shutdown instructions are fixed at the switchboard, and, if the System was late, reserve your right to delay damages in writing (Clause 8.3).
- Check that the monitoring app is registered in your name as administrator and change the passwords (Clause 14.1). Remove the Installer's account when you no longer need its support.
- Tell your property insurer about the System after Acceptance (Clause 16.2).
Warranties
- Register the manufacturers' warranties in your name and keep the serial numbers. Report defects in writing with photographs — for anything that smells of burning, sparks, or lets water into the building, call the Installer at once and switch the System off using the shutdown procedure (Clause 13.3).
- Keep the monitoring data for each guarantee year. The Installer must report on the Guaranteed Output within 30 days after each year (Clause 12.3).
- Under the Civil and Commercial Code, a claim for a defect must be brought within one year after the defect appears. Do not wait for the end of the warranty period.
Signing
- A company signs through the director or directors named in its latest company affidavit, with the company seal if its rules require one. Electronic signatures and signed PDF copies are valid (Clause 22.5).
Author and sources
Compiled from the notes that accompany the English contract templates on this site, published by Phuwara Krobtaku (ภูวรา ครอบตะคุ), Thai attorney-at-law, licence no. 477/2558. The short answer and summary at the top of this page are put together by the site from the template's clause headings and notes. Statutes are quoted only in the official Thai text: Thai is the only official language of Thai legislation, and an unofficial translation can mislead. Article registry OKC-EDB584. If you reuse this content, please credit the author and link to the original.
Frequently asked questions
Does a Solar PV Supply and Installation Agreement need stamp duty in Thailand?
This Agreement is a hire of work contract. Stamp duty is 1 THB for every 1,000 THB or part of 1,000 THB of the Contract Price. On the price you entered, the duty on the original is the amount the system calculates from the figures entered, and each counterpart carries the amount the system calculates from the figures entered. The Installer pays the duty within 15 days after signing — in money to the Revenue Department if the price is 1,000,000 THB or more, or through the e-Stamp Duty system if the Agreement is signed electronically.
How should a Solar PV Supply and Installation Agreement be signed?
A company signs through the director or directors named in its latest company affidavit, with the company seal if its rules require one. Electronic signatures and signed PDF copies are valid (Clause 22.5).
What clauses does a Solar PV Supply and Installation Agreement on this site include?
Definitions and Interpretation; The System and the Works; Site Survey and Roof Structure; Permits, Notifications and Grid Connection; Conditions for Ordering and Installation; Design and Equipment; Installation on Site; Completion Date and Delay; Testing, Commissioning and Acceptance; Title and Risk; Price and Payment; Performance Guarantee; Warranties and Defects; Monitoring System, Data and Cybersecurity; Operation and Maintenance; Insurance; Liability; Termination; Force Majeure and Change in Law; Notices; Governing Law and Disputes; General
Thai law cited (official Thai text)
The 9 sections below are quoted from the official Thai text, the only official language of Thai legislation. No translation is given, because an unofficial translation can mislead; check the Royal Gazette before relying on them in court.
ประมวลกฎหมายแพ่งและพาณิชย์ มาตรา 224
หนี้เงินนั้น ให้คิดดอกเบี้ยในระหว่างเวลาผิดนัดในอัตราที่กำหนดตามมาตรา 7 บวกด้วยอัตราเพิ่มร้อยละสองต่อปี ถ้าเจ้าหนี้อาจจะเรียกดอกเบี้ยได้สูงกว่านั้นโดยอาศัยเหตุอย่างอื่นอันชอบด้วยกฎหมาย ก็ให้คงส่งดอกเบี้ยต่อไปตามนั้น
ส่วนที่ 1 การไม่ชำระหนี้
ประมวลกฎหมายแพ่งและพาณิชย์ มาตรา 224/1
ถ้าลูกหนี้มีหน้าที่ผ่อนชำระหนี้เงินเป็นงวด และลูกหนี้ผิดนัดไม่ชำระหนี้ในงวดใด เจ้าหนี้อาจเรียกดอกเบี้ยในระหว่างเวลาผิดนัดได้เฉพาะจากต้นเงินของงวดที่ลูกหนี้ผิดนัดนั้น
ส่วนที่ 1 การไม่ชำระหนี้
ประมวลกฎหมายแพ่งและพาณิชย์ มาตรา 373
ความตกลงทำไว้ล่วงหน้าเป็นข้อความยกเว้นมิให้ลูกหนี้ต้องรับผิดเพื่อกลฉ้อฉล หรือความประมาทเลินเล่ออย่างร้ายแรงของตนนั้น ท่านว่าเป็นโมฆะ
หมวด 2 ผลแห่งสัญญา
ประมวลกฎหมายแพ่งและพาณิชย์ มาตรา 381
ถ้าลูกหนี้ได้สัญญาไว้ว่าจะให้เบี้ยปรับเมื่อตนไม่ชำระหนี้ให้ถูกต้องสมควร เช่นว่าไม่ชำระหนี้ตรงตามเวลาที่กำหนดไว้เป็นต้น นอกจากเรียกให้ชำระหนี้ เจ้าหนี้จะเรียกเอาเบี้ยปรับอันจะพึงริบนั้นอีกด้วยก็ได้
หมวด 3 มัดจำและกำหนดเบี้ยปรับ
พ.ร.บ.ควบคุมอาคาร พ.ศ. 2522 มาตรา 21
ผู้ใดจะก่อสร้าง ดัดแปลง หรือเคลื่อนย้ายอาคารต้องได้รับใบอนุญาต จากเจ้าพนักงานท้องถิ่น หรือแจ้งต่อเจ้าพนักงานท้องถิ่น และดำเนินการตามมาตรา 39 ทวิ มาตรา 21 ทวิ การก่อสร้าง ดัดแปลง หรือเคลื่อนย้ายอาคารชนิดหรือประเภทที่ กฎกระทรวงกำหนดให้มีการตรวจสอบงานออกแบบ และคำนวณส่วนต่าง ๆ ของโครงสร้างอาคาร ผู้ขอรับใบอนุญาต หรือผู้แจ้งตามมาตรา 39 ทวิ ต้องจัดให้มีการตรวจสอบงานออกแบบ และคำนวณ ดังกล่าวตามหลักเกณฑ์ วิธีการ และเงื่อนไขที่กำหนดในกฎกระทรวง มาตรา 22 ผู้ใดจะรื้อถอนอาคารดังต่อไปนี้ ต้องได้รับใบอนุญาตจากเจ้าพนักงาน ท้องถิ่น หรือแจ้งต่อเจ้าพนักงานท้องถิ่นและดำเนินการตามมาตรา 39 ทวิ (1) อาคารที่มีส่วนสูงเกินสิบห้าเมตรซึ่งอยู่ห่างจากอาคารอื่นหรือที่สาธารณะน้อย กว่าความสูงของอาคาร
พระราชบัญญัติควบคุมอาคาร พ.ศ. 2522 (ฉบับปรับปรุง 2558 ของสำนักงานคณะกรรมการกฤษฎีกา)
พ.ร.บ.วิศวกร พ.ศ. 2542 มาตรา 45
ห้ามมิให้ผู้ใดประกอบวิชาชีพวิศวกรรมควบคุม หรือแสดงด้วยวิธีใด ๆ ให้ผู้อื่น
พระราชบัญญัติวิศวกร พ.ศ. 2542
พ.ร.บ.ว่าด้วยข้อสัญญาที่ไม่เป็นธรรม พ.ศ. 2540 มาตรา 4
ข้อตกลงในสัญญาระหว่างผู้บริโภคกับผู้ประกอบธุรกิจการค้า หรือวิชาชีพ หรือในสัญญาสำเร็จรูป หรือในสัญญาขายฝากที่ทำให้ผู้ประกอบธุรกิจการค้า หรือวิชาชีพ หรือผู้กำหนดสัญญาสำเร็จรูป หรือผู้ซื้อฝากได้เปรียบคู่สัญญาอีกฝ่ายหนึ่งเกินสมควร เป็นข้อสัญญาที่ไม่เป็นธรรม และให้มีผลบังคับได้เพียงเท่าที่เป็นธรรมและพอสมควรแก่กรณีเท่านั้น
พระราชบัญญัติ ว่าด้วยข้อสัญญาที่ไม่เป็นธรรม พ.ศ. 2540
พ.ร.บ.ว่าด้วยข้อสัญญาที่ไม่เป็นธรรม พ.ศ. 2540 มาตรา 8
ข้อตกลง ประกาศ หรือคำแจ้งความที่ได้ทำไว้ล่วงหน้า เพื่อยกเว้นหรือจำกัดความรับผิดเพื่อละเมิดหรือผิดสัญญาในความเสียหายต่อชีวิต ร่างกาย หรืออนามัยของผู้อื่น อันเกิดจากการกระทำโดยจงใจหรือประมาทเลินเล่อของผู้ตกลง ผู้ประกาศ ผู้แจ้งความ หรือของบุคคลอื่นซึ่งผู้ตกลง ผู้ประกาศ หรือผู้แจ้งความต้องรับผิดด้วย จะนำมาอ้างเป็นข้อยกเว้นหรือจำกัดความรับผิดไม่ได้
พระราชบัญญัติ ว่าด้วยข้อสัญญาที่ไม่เป็นธรรม พ.ศ. 2540
ประมวลรัษฎากร มาตรา 118
ตราสารใดไม่ปิดแสตมป์บริบูรณ์ จะใช้ต้นฉบับ คู่ฉบับ คู่ฉีก หรือสำเนาตราสารนั้นเป็นพยานหลักฐานในคดีแพ่งไม่ได้ จนกว่าจะได้เสียอากรโดยปิดแสตมป์ครบจำนวนตามอัตราในบัญชีท้ายหมวดนี้ และขีดฆ่าแล้ว แต่ทั้งนี้ ไม่เป็นการเสื่อมสิทธิที่จะเรียกเงินเพิ่มอากรตามมาตรา 113 และมาตรา 114
บทบัญญัติ (ถ้อยคำตามเว็บกรมสรรพากร)